Selkirk Waterfront Way
Selkirk’s Waterfront Way is a scenic site offering views of Lake Erie, Selkirk Creek and a forested environment. This site features an existing trail with a pedestrian bridge connecting Erie Street South to Blue Water Parkway.
Status and timeline
See an overview of the project timeline below.
Spring/Summer 2022 - complete all the public consultation, final conceptual design and survey work
Summer 2022 into early 2023 - complete detailed engineering analysis, archaeological and environmental work
Spring 2023 - secure approvals from all review agencies (Long Point CA, DFO, Ministry of Tourism, Culture & Sport)
Summer 2023 - issue tender
Summer 2024 - engineering approvals and third-party permitting
July to September 2025 - construction and completion
Project contact
For more information on Selkirk Waterfront Way, contact Community Development & Partnerships.
Contact Us
Community Development & Partnerships
53 Thorburn Street South,
Cayuga, Ontario
Canada, N0A 1E0
Email Community Development & Partnerships