6.4 Caledonia Master Servicing Plan (MSP)
Daily Operations Guide, Engineering & Capital Works, Key Consideration
The Caledonia Master Servicing Plan (MSP) is a long-term infrastructure planning study that will identify the water, wastewater, stormwater, and transportation improvements required to support anticipated growth in the community. The study will establish a coordinated servicing strategy to guide future development, capital investment, and growth management decisions.
Details
| Key Consideration | Caledonia Master Servicing Plan (MSP) |
|---|---|
| Description | Guides long-term infrastructure planning and investment to support Caledonia's projected growth and align future servicing needs. |
| Work Plan Alignment | Master Servicing Plans |
| Department | Engineering & Capital Works |
| Division | Water & Wastewater Engineering |
Why it matters
-
Supports responsible growth by ensuring infrastructure capacity keeps pace with projected development.
-
Provides the long-term infrastructure strategy needed to guide growth and land use decisions in Caledonia.
-
Identifies future capital investments required for water, wastewater, stormwater, and transportation services.
-
Informs Development Charges studies, helping ensure growth-related infrastructure costs are recovered from development where appropriate.
-
Supports timely processing of development applications by establishing a clear servicing framework.
-
Reduces the need for reactive infrastructure decisions by enabling proactive, coordinated planning.
-
Helps Council prioritize infrastructure investments and make informed decisions on future growth and servicing needs.
Background
Haldimand County completed its last Master Servicing Plan (MSP) for Caledonia in 2020. While the study was completed, it was not presented to Council or the public due to the COVID-19 pandemic and remains in draft form. Several recommendations from the draft MSP have since been implemented or incorporated into the County’s 10-year capital forecast.
To ensure servicing strategies remain current and aligned with growth projections, the County updates MSPs approximately every six years for its urban communities. The current Caledonia MSP update aligns with this review cycle and is expected to be completed and presented to Council in fall 2027.
Current status
The contract has been awarded to J.L. Richards & Associates Limited in May 2026. Existing conditions assessment and servicing review are underway as part of the study's technical analysis.
Future considerations
Public Information Centres (PICs) are planned for fall 2026 and spring 2027.
The final MSP is expected to be presented to Council in fall 2027. The study may identify significant infrastructure investments needed to support future growth in Caledonia.
Ongoing coordination with Finance will help align the MSP with the Development Charges study.