Gypsum Mine Culvert Liner
Location: Caledonia Soccer Complex Road
Timeline: Mid-February to Mid-April
Project number: ENG-51-2025
Project lead: Mark Long
Ward: 3
Work planned
- Rehabilitation of the culvert on the Gypsum Mine Tract Trail
Additional information
The road in the culvert area will be closed for approximately one month from the start date to complete the repairs.
Highway 54 Bridge Removal & Grand Vista Trail 2 Extension
Location: Munsee Street North/Highway 54, Cayuga
Timeline: By-pass road complete, Trailhead completion in Spring 2026
Project number: ENG-54-2025
Project lead: Mark Long
Ward: 2
Work planned
- Removal of the existing rail overpass bridge on Haldimand Road 54/Munsee Street North and replacement with a new road profile has been completed.
- Creation of an AODA-compliant trailhead and parking area for the Grand Vista Trail
- The Grand Vista trailhead will be completed Mid-June with hydroseeding to follow.
Additional information
A public open house was held on February 18, 2025, to review the design of this project and answer any questions. If you require further information, please contact engineering@haldimandcounty.on.ca.
62 - 48 Caithness Street West Retaining Wall Replacement
Location: 62 - 48 Caithness St W, Caledonia
Timeline: Late Summer 2026 - Late Fall 2026
Project number: ENG-56-2026
Project lead: Mark Long
Ward: 3
Work planned
- Replacement of retaining wall and installation of AODA-compliant sidewalk
Boston Creek Bridge Rehabilitation
Location: Haldimand Road 9 - 3 km N of Fourth Line, Caledonia
Timeline: March 23, 2026 - mid-September 2026
Project number: ENG-50-2026
Project lead: Mark Long
Ward: 3
Work planned
- Rehabilitation of the bridge
Additional information
- Bridge will be open for the duration of repairs with lane restrictions in place.
Caithness Street Culvert Rehabilitation
Location: Caithness Street - 0.4 km W of McClung Rd, Caledonia
Timeline: April 20, 2026 - mid-August 2026
Project number: ENG-54-2026
Project lead: Mark Long
Ward: 3
Work planned
- Rehabilitation of the concrete culvert
- Installation of new AODA compliant sidewalk to connect to McClung Rd
- Asphalt replacement on the road from the culvert to McClung Rd with a paved shoulder on the South side
Additional information
- The work will be completed in two stages:
- First stage: culvert work
- Second stage: road works and sidewalk installation
- Caithness Street will be open to traffic with lane restrictions and portable traffic signals for duration of repairs
Haldimand Road 56 North & South Culvert Replacements
Location: Haldimand Road 56 - 0.5 km N of Concession 2 Road & 0.1 km S of Haldimand Road 9, York
Timeline: Mid-July 2026 to late-November 2026
Project number: ENG-53-2026
Project lead: Mark Long
Ward: 3
Work planned
- Replacement of both concrete box culverts.
Hart Road Bridge Rehabilitation
Location: Hart Road - 0.3 km N of Swayze Road, Canborough
Timeline: Mid-July 2026 - Mid-August 2026
Project number: ENG-51-2026
Project lead: Mark Long
Ward: 6
Work planned
- Rehabilitation of the bridge
Junction Road Culvert Replacement
Location: Junction Road - 0.16 km N of Haldimand Road 17, North Cayuga
Timeline: Mid-July 2026 to late-November 2026
Project number: ENG-53-2026
Project lead: Mark Long
Ward: 2
Work planned
- Replacement of existing culvert with a concrete box culvert