62 - 48 Caithness Street West Retaining Wall Replacement
Location: 62 - 48 Caithness St W, Caledonia
Timeline: Late Summer 2026 - Late Fall 2026
Project number: ENG-56-2026
Project lead: Mark Long
Ward: 3
Work planned
- Replacement of retaining wall and installation of AODA-compliant sidewalk
Caithness Street Culvert Rehabilitation
Location: Caithness Street - 0.4 km W of McClung Rd, Caledonia
Timeline: April 20, 2026 - mid-August 2026
Project number: ENG-54-2026
Project lead: Mark Long
Ward: 3
Work planned
- Rehabilitation of the concrete culvert
- Installation of new AODA compliant sidewalk to connect to McClung Rd
- Asphalt replacement on the road from the culvert to McClung Rd with a paved shoulder on the South side
Additional information
- The work will be completed in two stages:
- First stage: culvert work
- Second stage: road works and sidewalk installation
- Caithness Street will be open to traffic with lane restrictions and portable traffic signals for duration of repairs
Haldimand Road 56 North & South Culvert Replacements
Location: Haldimand Road 56 - 0.5 km N of Concession 2 Road & 0.1 km S of Haldimand Road 9, York
Timeline: Mid-July 2026 to early October 2026
Project number: ENG-53-2026
Project lead: Mark Long
Ward: 3
Work planned
- Replacement of both concrete box culverts.
Hart Road Bridge Rehabilitation
Location: Hart Road - 0.3 km N of Swayze Road, Canborough
Timeline: July 2026 - September 2026
Project number: ENG-51-2026
Project lead: Mark Long
Ward: 6
Work planned
- Rehabilitation of the bridge
Additional information
Hart Road between Swayze Road and Canborough Road will be closed for the duration of the repairs.
Junction Road Culvert Replacement
Location: Junction Road - 0.16 km N of Haldimand Road 17, North Cayuga
Timeline: Mid-July 2026 to October 2026
Project number: ENG-53-2026
Project lead: Mark Long
Ward: 2
Work planned
- Replacement of existing culvert with a concrete box culvert